Your lawn is important to us
When we dig the footings, we bring our bobcat in on plywood to protect your grass.
|
|
 |
Digging the footings
The bobcat has a 18 inch diameter auger. We can dig fast and year round with this bobcat.
|
|
 |
Verifying depth
Before we pour our concrete the building inspector must check the depth and bell of each footing. In our region of Minnesota, the frost-line is 42.
|
|
 |
Ledger boards
We set the ledger board at least 3 inches below the door to avoid water damage. We use a stainless steel flashing that won't corrode or rust.
|
|
 |
The framing
We hang and level the first rim joist and square it with the ledger.
|
|
 |
Framing on...
We use pressure treated southern yellow pine with a #1 grade.
|
|
 |
Setting 6x6 posts
After the framing is up, we set our 6x6 support posts. Sometimes we cover the posts with a fascia or decorative sleeve.
|
|
 |
Decking
Once the framing is finished, we start installing the decking.
|
|
 |
Railing
We install all of the rail posts then, install the railing.
|
|
 |
Aluminum railing
This aluminum railing has glass pickets to preserve the view of the yard.
|
|
 |
low-maintenance decking
This is decking an aluminum decking powder-coated to look like real wood. The balusters are powder-coated to match.
|
|
 |
Viola!
The fascia is hung, lights are installed and wired, and the deck is completed!
|
|